THE TRAM VENTURES FORTH

On 11 November 2017

Testing and trial phase

This image has an empty alt attribute; its file name is luxtram_premiers-pas_250x540.png

From 12 July 2017, Luxtram will begin the “testing and trial” phase during which all the tramway’s functionalities will be checked. 
 
This phase will be conducted in several stages: 

  • The overhead contact line will be electrified from 10 July: the tramway overhead line will be electrified round the clock with 750 DC volts.
  • The first tram will run on Kirchberg: from 12 July and until the end of October, the tram will run on its platform and will share the public space with other users.
  • Test run: in November, the tram will run under normal operating conditions, but without passengers. 
  • Full commercial service: will begin from 10 December 2017 when the tram will welcome its first passengers on board.

Take a look at Luxtram’s new informercial!

For all further information, please contact Luxtram on info@luxtram.lu.