THE TRAM VENTURES FORTH
On 11 November 2017Testing and trial phase

From 12 July 2017, Luxtram will begin
the “testing and trial” phase during which all the tramway’s functionalities
will be checked.
This phase will be conducted in several stages:
- The overhead contact line will be electrified from 10 July: the tramway overhead line will be electrified round the clock with 750 DC volts.
- The first tram will run on Kirchberg: from 12 July and until the end of October, the tram will run on its platform and will share the public space with other users.
- Test run: in November, the tram will run under normal operating conditions, but without passengers.
- Full commercial service: will begin from 10 December 2017 when the tram will welcome its first passengers on board.
Take a look at Luxtram’s new informercial!
For all further information, please contact Luxtram on info@luxtram.lu.